+7 (499) 390-91-21 Message to Telegram Our YouTube channel Message to MAX

Проект: Infectious Diseases Hospital in TINAO

Uninterrupted power supply to medical units, intensive care units, laboratory, oxygen station, etc.

A coronavirus center was built near the village of Golokhvastovo in the Voronovskoye settlement. About 11,000 construction workers and more than 1,500 pieces of equipment worked here every day and around the clock. The construction lasted a month. This is a full-fledged infectious diseases hospital that will continue to function after the end of the coronavirus pandemic. The center became part of the V.P. Demikhov Municipal Clinical Hospital No. 68.

7 days - project completion and UPS delivery
3 days - installation and commissioning
Limited dimensions of the systems
A special category of consumer power supply
More than 1 MW total UPS capacity

Manufactured equipment